    Implementation of two projects in Mobarakeh Steel

    شناسه : 27496 02 شهریور 1399 - 12:25
    While announcing this news, the director of Mobarakeh Steel's steelmaking and continuous casting department said: "Following the increase in the country's electricity consumption in summer and the restrictions imposed on the steelmaking sector by the national electricity grid, the company's management decided to keep this equipment ready for a valuable opportunity." To carry out major repairs in the area of ​​steelmaking and continuous casting.Gholamreza Salimi added: "Using the capacity of the repair forces inside the area and the support team (such as repairs and central repair shop, technical inspection, etc.), repair and corrective activities were carried out on the equipment to prepare the equipment for use to increase production time." Increase production and achieve better records.
    پ
    پ

    In line with its commitment to its social responsibilities, the management of Mobarakeh Steel Company, in cooperation with the Isfahan Regional Electricity Authority, planned and carried out major repairs of the steelmaking and continuous casting area during the hottest days of the summer in a coherent program. All over the country, dear citizens, do not face the problem of electricity shortage or blackout.

    While announcing this news, the director of Mobarakeh Steel  steelmaking and continuous casting department said: “Following the increase in the country’s electricity consumption in summer and the restrictions imposed on the steelmaking sector by the national electricity grid, the company’s management decided to keep this equipment ready for a valuable opportunity.” To carry out major repairs in the area of ​​steelmaking and continuous casting.

    Gholamreza Salimi added: “Using the capacity of the repair forces inside the area and the support team (such as repairs and central repair shop, technical inspection, etc.), repair and corrective activities were carried out on the equipment to prepare the equipment for use to increase production time.” Increase production and achieve better records.

     

    *** Ready-to-operate equipment to increase production

    He said: “Some of the measures taken in this regard are: performing periodic planned repairs and replacing part of the platform structure and repairing slabs of the slag enclosure by spending about 2,500 hours, periodic repairs and replacing part of the platform structure in the furnace. 4 by spending about 2,200 hours; Replacing the main beam of the roof, replacing the Rockers of Furnace No. 7, spending about 13,000 man-hours.

    Salimi stated that great measures have been taken in the field of continuous casting, and said: in the four-day repairs of the No. 1 casting machine, the pulling of the pulling and straightening rollers as well as their liner were done in several stages and work fronts. In addition to industrial cleaning of the machine that can not be done in normal shutters, flushing machine cleaning, demolition and concreting in the middle of the line, installation of slide gate heat exchanger to reduce hydraulic temperature, disassembly and assembly of segments 1 and 2 of both lines and replacement of the oscillator .

     

    *** Mobarakeh Steel Development Activities

    The director of Mobarakeh Steel continuous steelmaking and casting department, in this regard, emphasizing that it is not possible to perform all these activities in one day according to the chart load, said: Flushing of all casting machines, wrenching of rails and rails, ROW O_P unit 28, separation of industrial water unit Casting from the steelmaking unit and separating the primary water of casting machines 3 and 4 Another part of these measures has been limited at this time.

    He went on to announce the replacement of the traverse of crane number 25 by spending about 1,200 man-hours and specified: “This is the first time this activity has been done on this crane and it has been done in several days.”

    Emphasizing that the one-day planned annual repairs of the steelworks in this period were carried out with appropriate quality, Salimi continued: In the annual shuttle, routine service of all metal cold boards and power centers in the area, total fluid control systems and industrial water was performed.

    In conclusion, he noted: “Considering the development of the steel hall to install two new cranes with a capacity of 350 tons, measures related to resolving related disputes, including the relocation of the dust duct of patty furnaces, are also underway in these planned repairs.”

     